Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Jan
Feb
Apr
May
June |
Hope4Hannah is Conceived / Committee Formed / Planning Meeting Conducted
Home Design / Web Design / Video & Flyers Created & Distributed / Perk Test
Minor Complications, but Permits Finally Approved
Septic System Installed / Property Surveyed / CIGI Modeling Fund Raiser / Celebration
Singers Benefit Concert / Golf Tournament Fund Raiser
Excavation / Footings Dug and Concrete Poured
Block Work / Sub-Floor / Floor
Walls Framed
Roof Trusses, Decking, & Shingles
Roof Complete / Windows Installed
Exterior Doors & Facia
Electrical & Plumbing Installation
Heating & Air Completed, Passed Electrical & Plumbing Inspections, Wall Insulation Installed, Drywall Installed, Fireplace Installed, and Exterior Brick Completed
Vinyl Siding, Interior Trim/Doors, Cabinets, Interior Painting, Ceramic Tile, Hardwood Floors, Final Electrical & Fixtures
Porch Stairs & Railing, Final Interior Trim, Carpet, Countertops, Landscaping, & Dedication
|